    Hi Shah,


    Thanks for reaching out! Happy to help with this. We haven't changed the way Projects are tracked recently so I'm really curious to know more about what you're seeing.


    The Project tracker has always required choosing a percentage complete for a milestone with a slider, but the percent is automatically set based on any subtasks under it that have been completed. Could that be the difference?


    If not, could you send me more details, screenshots or a screen recording?


    Thanks!

    Kyle